Talk to us
Systems by size
Small SystemsMedium SystemsLarge / Utility-Scale SystemsUPS Solutions
Every system
Arctium FLEXArctium EDGEArctium GeluArctium BlockArctium GridArctium VRLA batteriesConversion & PCSEMS & controlsEV charging
Programs
BC Hydro ESIGlobal AdjustmentCapacity AuctionFast frequency responseDemand chargesClean Technology ITCClean Electricity ITCSave on EnergyCIB & Indigenous equitySREPs / watchlist
Talk to us
Packages

Over 40 packages, already engineered

Forty-one complete designs across twelve markets, ready to configure and land. Here are the six most popular.

41Packages engineered
12Markets served
6Shown here
Data centresManufacturingMiningOil & gasHealthcareCommercial & strataRemote communitiesWater & wastewaterTelecomTransport & portsAgricultureGovernment & defence
What is shown, and what is not

These are conceptual architectures — equipment and how it relates. Ratings, protection settings, coordination studies and our newer topologies go to clients under NDA.

Remote community · northern Canada
Remote community · northern Canada
DATA CENTRES  ·  P21

Data Centre Backup

Grid and generator on automatic transfer, UPS across the gap, cooling on the essential bus.

P21  //  GRID + GENERATOR + UPS
WITH UPS
GridService Protutility protPCC BrkGeneratorGen BrkATSopen transitionSwitchboardexisting or newLoad BrkLoadsCool BrkCoolingIn BrkUPS FrameOut BrkCritical LoadBatt BrkUPS BatteryEMSAC BUSstatic bypasscontrol / comms
Grid
Generator
BESS
Breaker
Switchboard
ATS
Protection Relay
Loads
Critical Load
UPS
EMS / Controller
Cooling / CDU
Swipe to pan →
Scale 250 kW – 2 MW critical Drawing Conceptual, not for construction
MANUFACTURING  ·  P12

Hybrid Resilience Plant

Storage answers instantly and bridges the generator start; the site islands on the PCC.

P12  //  GRID + BESS + GENERATOR
NO UPS
GridPCC Protanti-islandPCC BrkislandingBESSBatt DC Protbrk + fusePCSGFMBESS BrkBMSGeneratorGen BrkXFMRif req.XFMRif req.Switchboardexisting or newLoad BrkLoadsEMSAC BUScontrol / comms
Grid
Generator
BESS
PCS / Inverter
DC Protection
Breaker
Switchboard
Transformer (if required)
Protection Relay
Loads
EMS / Controller
BMS
Swipe to pan →
Scale 500 kW – 5 MW protected Drawing Conceptual, not for construction
COMMERCIAL & INDUSTRIAL  ·  P05

Grid Smoothing & Peak Shaving

Discharge into the measured demand interval so the billed peak falls.

P05  //  GRID + BESS
NO UPS
GridPCC Protanti-islandPCC BrkBESSBatt DC Protbrk + fusePCSGFLBESS BrkBMSXFMRif req.Switchboardexisting or newLoad BrkLoadsEMSAC BUScontrol / comms
Grid
BESS
PCS / Inverter
DC Protection
Breaker
Switchboard
Transformer (if required)
Protection Relay
Loads
EMS / Controller
BMS
Swipe to pan →
Scale 125 kW – 2 MW reduction Drawing Conceptual, not for construction
MINING & HEAVY INDUSTRY  ·  P31

Partial Diesel Replacement

The set carries average load; the battery takes peaks and step loads.

P31  //  BESS + GENERATOR
PARTIAL
BESSBatt DC Protbrk + fusePCSGFMBESS BrkBMSGeneratorGen BrkXFMRif req.XFMRif req.Switchboardexisting or newLoad BrkLoadsCool BrkCoolingEMSAC BUS / ISLAND BUScontrol / comms
Generator
BESS
PCS / Inverter
DC Protection
Breaker
Switchboard
Transformer (if required)
Loads
EMS / Controller
BMS
Cooling / CDU
Swipe to pan →
Scale 500 kW – 5 MW support Drawing Conceptual, not for construction
REMOTE & OFF-GRID  ·  P09

Renewable Island Microgrid

A grid-forming PCS holds the island; renewables serve load, then charge.

P09  //  BESS + RENEWABLE
NO UPS
BESSBatt DC Protbrk + fusePCSGFMBESS BrkBMSSolar PVPV DC Protfuse/SPD/RSDPV InverterGFLPV BrkXFMRif req.XFMRif req.Switchboardexisting or newLoad BrkLoadsEMSISLAND BUScontrol / comms
Solar / Wind
BESS
PCS / Inverter
DC Protection
Breaker
Switchboard
Transformer (if required)
Loads
EMS / Controller
BMS
Swipe to pan →
Scale 100 kW – 5 MW island Drawing Conceptual, not for construction
TRANSPORT & FLEETS  ·  P38

EV Hub with BESS Buffer

The service is sized to the average session load, not the simultaneous maximum.

P38  //  GRID + BESS
EV CHARGING
GridPCC Protanti-islandPCC BrkBESSBatt DC Protbrk + fusePCSGFLBESS BrkBMSXFMRif req.Switchboardexisting or newLoad BrkLoadsEVSE BrkEV ChargersEMSAC BUScontrol / comms
Grid
BESS
PCS / Inverter
DC Protection
Breaker
Switchboard
Transformer (if required)
Protection Relay
Loads
EMS / Controller
BMS
EV Chargers
Swipe to pan →
Scale Sized from charger duty Drawing Conceptual, not for construction
Innovation

The dual-PCS package

Two converters back to back with the battery on the DC link, and the whole site feeder running through it.

P41  //  ON-SITE GENERATION + BESS + MV CONVERTER
CAMPUS
CAMPUS GENERATION ISLANDthe campus power plantBOUNDARY CONVERTER (MV)series device — two sets, 2NDATA BUILDING — NO FACILITY UPSno second battery, no UPS roomGen Set AGen Brkrecip or turbineGen Set BGen Brkn sets, one shownHeat RecoveryGen Brksteam, if fittedBESSBatt DC Protbrk + fusePCSGFMBESS BrkFeeder BrkMVConv. Aplant sideConv. Bbuilding sideDC Protbrk + fuseLink BatteryBldg XFMRMV / LVBldg Switchboardlow voltageIT BrkIT RacksCool BrkCooling / CDUHouse BrkHouse LoadsCAMPUS MV BUSCOMMON DC LINK
Generator
BESS
PCS / Inverter
DC Protection
Breaker
Switchboard
Transformer (if required)
Loads
Critical Load
Cooling / CDU
Swipe to pan →

Load swings never reach the generation

Converter A holds plant-side current steady through a step change.

Source events never reach the load

A sag is absorbed on the DC link; converter B keeps holding the facility.

One battery, two jobs

Firms the plant and carries the load — instead of a battery plus a UPS.

It is a series device, and we say so

The whole load passes through it, so redundancy and bypass are designed in.